Tuesday
Sep292009

Derrick Lifting

The first Coker Derricks were lifted into place this week. The pictures speak for themselves.

Friday
Sep252009

4 Building Sections Making Up PDC for Sulfur Block

Friday
Sep252009

Coker and DHT-3 Equipment Setting

Blowdown Settling Drum set in the Coker area...

DHT-3 Compressors set in DHT-3 area...

Sunday
Sep202009

Coker Complex PDC Building Sections on Foundation

Thursday
Sep032009

Final Lift for LR1800

As the last lifting task for Mammoet's LR1800 this tower was positioned on it's foundation in the Coker by 09:00hrs this morning.

Breakdown and disassembly began today and her next work location is a nuclear power plant in Pennsylvania.